HomeMy WebLinkAbout2009-11-03 WUCFD MINUTESWATER UTILITIES COMMUNITY FACILITIES DISTRICT
(APACHE JUNCTION WATER COMPANY)
CITY OF APACHE JUNCTION, ARIZONA
REGULAR MEETING
NOVEMBER 3, 2009
The regular meeting of the District Board of the Water
Utilities Community Facilities District (Apache Junction Water
Company), City of Apache Junction, Arizona, was held on November
3, 2009, at the Apache Junction City Council Chambers pursuant
to the notice required by law.
CALL TO ORDER
Chairperson Insalaco called the meeting to order at 6:00
p.m.
ROLL CALL
Board Members Present:Chairperson Insalaco
Vice Chairperson R.E. Eck
Mr. Doug Coleman
Mr. Rick Dietz
Mr. Jeff Serdy
Mr. Chip Wilson
Staff Present:
(Mrs. Barker was absent.)
George Hoffman, District Manager
Kathleen Connelly, District Clerk
Frank Blanco, District Director
Giao Pham, District Engineer
John White, District Finance Manager
Kay Bigelow, District Legal Counsel
Others Present:Bryant Powell, Assistant City Manager
Hazel Randall, District Admin. Asst.
APPROVAL OF MINUTES OF OCTOBER 6,
2009
)Mr. Dietz MOVED THAT THE
MINUTES OF ,OCTOBER 6, 2009, BE APPROVED.
Water Utilities Community Facilities District
Meeting Minutes of November 3, 2009
Page 1 of 8
Mr. Wilson SECONDED THE
MOTION.
VOTE:Unanimous.
The motion carried.
Chairperson Insalaco stated
they are waiting for the district legal counsel for the next
item so they will proceed with the district manager report.
DISTRICT MANAGER REPORT
None.
DISTRICT DIRECTOR REPORT
District Director Frank Blanco updated the board on the Mesa
Interconnect status, the water system update and the Central
Arizona Project Fall 2009 Salt River Siphon Outage.The
interconnect is about 90% completed.They received the shipment
of pumps and motors on Wednesday last week.They have been
installed in the pump house.The pumps are capable of supplying
500,000,000 gallons per day.They have a blind flange on the
site which will allow for expansion in the future if required.
They received their green tag from Mesa and the tag from Salt
River Project today.The latter will allow them to install a
meter and provide electrical service to the facility.The
contractors will be able to start testing the site.Currently
the city is not receiving any water from Arizona Water.The
City of Mesa is not treating any water from Central Arizona
Project because of the canal outage.Arizona Water was asked to
discontinue their delivery of Central Arizona Project water or
any water from Mesa to the district.The capacity is 1.6
million gallons per day using Wells 5 and 6.Both sites had new
pumping equipment and improvements.The current demand is about
1.5 million gallons per day.The storage tanks are very close
to what they are normally.Boosters are operating normally.
They have started an inventory of pipelines, valves and hydrants
in order to start doing some proactive flushing of mains.This
requires about 80,000 gallons for each flush.
Water Utilities Community Facilities District
Meeting Minutes of November 3, 2009
Page 2 of 8
Vice Chairperson Eck commented if they do not clear it, they do
not get the water.
District Director Frank Blanco stated that is correct.It is
important they are doing that.They will do the southeast area
of the city next.The one they just did was at 1:00 a.m. so
there were no complaints from residents or businesses.
Vice Chairperson Eck asked if the customers would be getting
something in their billing notifying of them of the district
having a new water supply.
District Director Frank Blanco stated they have not done that
but it is a very good point.They can communicate that to the
customers be means of the billing.
Vice Chairperson Eck commented Well 6 was at 1,200 or 1,500 TDS.
District Director Frank Blanco stated it was very high.
Vice Chairperson Eck commented they have used some wells down in
that area, but Mesa got lucky and got good wells in that area,
plus the Central Arizona Project in that area is less than half
the TDS that what we were getting.The water has a potential to
be pretty nice water.
District Director Frank Blanco stated they hope to see a great
improvement.They did have a press release recently with Mr.
Insalaco coming out for it.Perhaps an insert in the next bill
would be a good idea.
Vice Chairperson Eck commented he thinks public notification
would do it.As prices change due to the arsenic costs and the
tie-ins, it might help us to educate them.
District Director Frank Blanco stated the storage capacity is
currently 1,000,000 gallons at 16th Avenue and Buena Vista.
There is another 1,000,000 gallons at Baseline Avenue.However,
our peak hour of maximum daily demand is 3.79; it is a
calculated value based on the maximum day and how much water
would be required to serve the public and meet fire demands.
There is a need for additional storage.As part of the
interconnect project, he has contacted the Water Infrastructure
Water Utilities Community Facilities District
Meeting Minutes of November 3, 2009
Page 3 of 8
Finance Authority and proposed expanding the scope.They have
been receptive and have agreed to that.The intent is to use
the funds not used on the interconnect to construct additional
storage which is already needed.He will come back to the board
for approval of that at a future date.He then described how we
get water from the Colorado River.The siphon pipeline is the
major reason we will be down for a period of time in November.
There is a recharge project south of the Apache Junction that is
called the Superstition Mountains Recharge Project.It has been
recently studied by the Bureau of Reclamation.The Central
Arizona Water Conservation District will be using some of their
land for a regional recharge facility, which is closer to the
city than other facilities on the west side of the valley.The
likelihood of the district getting water that is recharged in
the West Valley is not really there.This new facility is a
good thing for Apache Junction to recharge excess Central
Arizona Project water at a future date.
Vice Chairperson Eck commented they can still do recharge as
long as it is tied in to the system.Currently it is tied in to
the system even though it is a couple hundred miles away or
whatever.They can do their recharge credits.
District Director Frank Blanco stated it is in the Phoenix AMA
and when they go to a recharge facility, the current rules state
they can recharge at that facility and recover from a well in
our district or area.
District Legal Counsel Kay Bigelow stated it has to be in the
AMA.
District Director Frank Blanco stated the upstream work includes
the repair of guard and clamshell valves.It is a structure on
the Salt River siphon.Downstream work includes valve repairs
at the Brady pumping station, valve replacement at Red Rock
pumping plant, and inspection at Twin Peaks pumping plants and
another pumping plant.The clamshell valves will evacuate the
Central Arizona Project canal in case of having a very high
level in the canal.It has only happened once thus far.
Vice Chairperson Eck asked what it does essentially.
Water Utilities Community Facilities District
Meeting Minutes of November 3, 2009
Page 4 of 8
District Director Frank Blanco stated it reduces the canal
levels in the Central Arizona Project.It was so close to the
top it was about to flow over.
Vice Chairperson Eck commented it is so they will not get such a
build up.
District Director Frank Blanco stated it is so it does not
flood, overflow and cause damage.It really discharges into the
Salt River, not the canal.He showed a diagram of how it works,
pictures of the fish barrier, and the schedule of the outage.
The district will not be able to take its treated Central
Arizona Project water from Mesa or any Central Arizona Project
water from Mesa during this time.Water must be supplied by
district wells or emergency water from Arizona Water.
Vice Chairperson Eck asked if that is in November.
District Director Frank Blanco stated it is basically all of
November.
Vice Chairperson Eck commented he wished they would consider
getting political in that matter and just show that this is just
a quarter of a percent of Mesa's daily water.For us, it is a
whole lot of water.It is a tiny issue for them but a huge
issue for us.He wished they could talk to them and explain
where they are coming from on it.Maybe they could get some
sympathy on where the district is coming from.He does not
think they are getting all this information.
District Director Frank Blanco stated they may be able to do
that somehow legally, maybe with a water delivery and use
agreement where we would pay them back the water.
District Legal Counsel Kay Bigelow stated that is correct.We
could do something, especially now that they are talking about
having an interconnect, as the district would not have to have a
three party contract with Arizona Water in the middle of it.
Vice Chairperson Eck commented that the one person with 33% is
out of it now.
Water Utilities Community Facilities District
Meeting Minutes of November 3, 2009
Page 5 of 8
District Legal Counsel Kay Bigelow stated they can start looking
at that and get back to him on it.
Mr. Dietz commented he stated they may have to draw from Arizona
Water.He asked if that could become a problem as they rely on
Mesa.
District Director Frank Blanco stated they do rely on Mesa.It
is a potential problem there.The emergency meter is still
connected, so technically we could still ask them for
groundwater.He is not sure how thin they are on water.They
could always potentially request that.He needs to meet with
the new person there and flesh those things out.He advised
them that even though they are not using the interconnect at
this time, we are still doing systems testing and are
troubleshooting the program.They are still on schedule for the
January date, if not sometime in December.
Vice Chairperson Eck commented this is a job well done.He held
in there with a lot of challenges and he has built a staff
around him that obviously respects him and works with him to get
this done.He would like to thank the entire department and
things are now going good in the water department.
District Director Frank Blanco stated he would like to thank the
public works department and finance for hanging in there and
helping them to get the projects done.
RESOLUTION NO. 2009-008, APPROVING
A SECTION 125 CAFETERIA PLAN FOR
FLEXIBLE SPENDING ACCOUNTS FOR
WATER DISTRICT EMPLOYEES
)District Legal Counsel Kay
Bigelow briefed the board on the item.
Chairperson Insalaco called
for any discussion.There being no discussion, he called for a
motion.
Mr. Coleman MOVED THAT
RESOLUTION NO. 2009-008, A RESOLUTION OF THE BOARD OF DIRECTORS
OF THE WATER UTILITIES COMMUNITY FACILITIES DISTRICT (CITY OF
APACHE JUNCTION, ARIZONA) APPROVING A SECTION 125 CAFETERIA PLAN
Water Utilities Community Facilities District
Meeting Minutes of November 3, 2009
Page 6 of 8
FOR FLEXIBLE SPENDING ACCOUNTS FOR WATER DISTRICT EMPLOYEES BE
APPROVED.
Mr. Dietz SECONDED THE
MOTION.
VOTE:Unanimous.
The motion carried.
DISTRICT TREASURER REPORT
None.
DISTRICT LEGAL COUNSEL REPORT
District Legal Counsel Kay Bigelow stated she would like to
second what Vice Chairperson Eck stated about Frank jumping in
on the interconnect project.This kept us in a position with
new development where they do not have to go out and build a
treatment plant right away.
ADJOURNMENT )
) Chairperson Insalaco
adjourned the meeting at 6:28 p.m.
ACCEPTED THIS 3RD DAY OF NOVEMBER , 2009,
BY THE CHAIRPERSON AND DISTRICT BOARD OF THE WATER UTILITIES
COMMUNITY FACILITIES DISTRICT (APACHE JUNCTION WATER COMPANY),
CITY OF APACHE JUNCTION, ARIZONA.
SIGNED AND ATTESTED TO THIS 3RD DAY OF NOVEMBER
2009.
,41..,,,„,
aohn S. Insalaco
Chairperson
Water Utilities Community Facilities District
Meeting Minutes of November 3, 2009
Page 7 of 8
ATTEST:
:athleen ConnellyKathleen Connelly
District Clerk
WATER UTILITIES COMMUNITY FACILITIES DISTRICT MINUTES
CERTIFICATION
I hereby certify that the foregoing minutes are a true and
correct copy of the minutes of the regular meeting of the Water
Utilities Community Facilities District of the City of Apache
Junction, Arizona, held on the 3rd day of November, 2009.I
further certify that the meeting was duly called and held and
that a quorum was present.
Dated this 6th day of November, 2009.
g-er--&-r4---671-4SKathleen Connelly 4
District Clerk
Water Utilities Community'Facilities District
Meeting Minutes of November 3, 2009
Page 8 of 8