HomeMy WebLinkAbout2013-07-02 WUCFD MINUTESWATER UTILITIES COMMUNITY FACILITIES DISTRICT
CITY OF APACHE JUNCTION, ARIZONA
REGULAR MEETING
JULY 2, 2013
The regular meeting of the District Board of the Water
Utilities Community Facilities District, City of Apache
Junction, Arizona, was held on July 2, 2013, at the Apache
Junction City Council Chambers pursuant to the notice required
by law.
CALL TO ORDER
Chairperson Insalaco called the meeting to order at 6:00
p.m.
ROLL CALL
Board Members Present:Chairperson Insalaco
Vice Chairperson Barker
Mrs. Evans
Mrs. Rizzi
Mr. Serdy
Mr. Waldron
Mr. Wilson
Staff Present:George Hoffman, District Manager
Kathleen Connelly, District Clerk
Frank Blanco, District Director
Joel Stern, District Legal Counsel
Giao Pham, Utility Director
Donna Meinerts, District Treasurer
John White, District Finance Manager
Others Present:Bryant Powell, Assistant City Manager
Hazel Randall, Administrative Assistant
APPROVAL OF MINUTES OF June 18,2013)
) Mr. Waldron MOVED THAT THE
MINUTES OF JUNE 18, 2013, BE APPROVED.
Water Utilities Community Facilities District
Meeting Minutes of July 2, 2013
Page 1 of 9
Vice Chairperson Barker
SECONDED THE MOTION.
VOTE:Unanimous.
The motion carried.
DISCUSSION OF PROPOSED BUDGET FOR
FISCAL YEAR 2013-2014 TO INCLUDE
PROPOSED RATES, FEES AND CHARGES,
CLASSIFICATION AND COMPENSATION
PLAN FOR DISTRICT EMPLOYEES
-)District Finance Manager
John White stated the budget includes a 3% increase which is the
same as what is proposed for the city.Rates are remaining the
same with a couple of exceptions that do not affect the ongoing
current customer base.One exception is system connection fees
which are for new customers and is a 2.7% increase consistent
with what they have done in past years.This usually rounds out
to $100 per residential connection.Another exception is the
proposal of a water resource acquisition fee which is $655.
This is a one-time fee that will be assessed against new
development and new connection.
FISCAL YEAR 2013-2014
CLASSIFICATION AND COMPENSATION
PLAN FOR DISTRICT EMPLOYEES
) Assistant City Manager
Bryant Powell stated this item pertains to the classification
and compensation plan.It is very similar to the one for the
city.It allows for the 3% general increase for employees in
the water district.
Mr. Waldron MOVED THAT
RESOLUTION NO. 2013-004,A RESOLUTION OF THE WATER UTILITIES
COMMUNITY FACILITIES DISTRICT (CITY OF APACHE JUNCTION, ARIZONA)
DECLARING AS A PUBLIC RECORD AND ADOPTING CERTAIN DOCUMENTS
FILED WITH THE DISTRICT CLERK ENTITLED "THE CLASSIFICATION PLAN
FOR FISCAL YEAR 2013-2014" AND "THE COMPENSATION PLAN FOR FISCAL
YEAR 2013-2014" BE APPROVED.
Water Utilities Community Facilities District
Meeting Minutes of July 2, 2013
Page 2 of 9
Vice Chairperson Barker
SECONDED THE MOTION.
VOTE:Unanimous.
The motion carried.
RESOLUTION NO. 2013-005, A
ADOPTING A PROPOSED BUDGET FOR
THE FISCAL YEAR BEGINNING JULY 01,
2013 AND ENDING ON JUNE 30, 2014;
ESTABLISHING A PUBLIC HEARING AND
DESIGNATING DATE, TIME AND LOCATION
BUDGET )
) Vice Chairperson Barker
MOVED THAT RESOLUTION NO. 2013-005, A RESOLUTION OF THE WATER
UTILITIES COMMUNITY FACILITIES DISTRICT (CITY OF APACHE
JUNCTION, ARIZONA) PURSUANT TO (Arizona Revised Statutes Title
48-016), ADOPTING A PROPOSED BUDGET FOR THE FISCAL YEAR
BEGINNING JULY 01, 2013 AND ENDING ON JUNE 30,2014; ESTABLISHING
A PUBLIC HEARING ON THE PROPOSED BUDGET; AND DIRECTING STAFF TO
SOLICIT COMMENTS FROM THE CITY OF APACHE JUNCTION ON THE
PROPOSED ANNUAL BUDGET BE APPROVED; AND I FURTHER MOVE THE
PUBLIC HEARING FOR FINAL BUDGET ADOPTION BE HELD ON AUGUST 06,
2013 AT 6:00 PM IN THE APACHE JUNCTION CITY COUNCIL CHAMBERS,
300 EAST SUPERSTITION BOULEVARD, APACHE JUNCTION, ARIZONA. I
FURTHER MOVE THAT WE APPROVE TEMPORARY PERSONAL LEAVE FOR
ELIGIBLE WATER DISTRICT EMPLOYEES FOR FISCAL YEAR 2013-2014
SUBJECT TO THE FOLLOWING TERMS:
1. ADDING FOUR HOURS OF TEMPORARY PERSONAL LEAVE FOR
ELIGIBLE WATER DISTRICT EMPLOYEES WORKING A 4-10
SCHEDULE,TWO HOURS OF WHICH WILL BE USED TO SUPPLEMENT
THE EMPLOYEES' BIRTHDAY LEAVE AND TWO HOURS OF WHICH
SHALL BE USED TO SUPPLEMENT VETERAN'S DAY HOLIDAY ON
NOVEMBER 11, 2013.
2. ADDING FOUR HOURS OF TEMPORARY PERSONAL LEAVE FOR
ELIGIBLE EMPLOYEES WORKING A 5-8 SCHEDULE, FOUR HOURS OF
WHICH SHALL BE USED DURING FISCAL YEAR 2013-2014.
3. ADDING TWO HOURS OF TEMPORARY PERSONAL LEAVE FOR ELIGIBLE
PART TIME EMPLOYEES, TWO HOURS OF WHICH SHALL BE USED
DURING FISCAL YEAR 2013-2014. ELIGIBLE PART TIME
Water Utilities Community Facilities District
Meeting Minutes of July 2, 2013
Page 3 of 9
EMPLOYEES ARE THOSE EMPLOYEES WHO REGULARLY WORK BETWEEN
24 AND 31 HOURS PER WEEK.
4. ELIGIBLE EMPLOYEES WHOSE BIRTHDAY FALLS IN THE MONTH OF
JULY 2013 OR AUGUST 2013 AND/OR ELIGIBLE EMPLOYEES WHO
REQUEST AND USE BIRTHDAY LEAVE DURING THE MONTH OF JULY
2013 OR AUGUST 2013 SHALL BE REQUIRED TO SUPPLEMENT THEIR
BIRTHDAY LEAVE WITH EARNED VACATION LEAVE OR EARNED
COMPENSATORY TIME.SUCH EMPLOYEES WILL HAVE AVAILABLE
TWO HOURS OF THIS TEMPORARY PERSONAL LEAVE FOR USE AT A
LATER DATE DURING FISCAL YEAR 2013-2014 SUBJECT TO THE
TERMS AND CONDITIONS AS SET FORTH IN THIS MOTION.
5. THIS TEMPORARY PERSONAL LEAVE WILL BE PLACED IN A
SEPARATE BILLING ACCOUNT APART FROM VACATION AND SICK
LEAVE; IT WIL BE CONSIDERED STRAIGHT TIME AND WILL NOT BE
USED IN THE CALCULATION OF OVERTIME OR CAUSE AN EMPLOYEE
TO BE PAID FOR OVER FORTY HOURS IN THE WORK WEEK; IT WILL
ONLY BE AVAILABLE FOR USE BEGINNING AUGUST 10, 2013 AND
UP TO AND INCLUDING JUNE 30, 2014; THERE WILL BE NO
CARRYOVER OF THIS LEAVE BEYOND JUNE 30, 2014; PRIOR TO
TAKING THIS LEAVE AN EMPLOYEE SHALL OBTAIN APPROVAL FROM
HIS/HER DEPARTMENT DIRECTOR.
6. THIS TEMPORARY PERSONAL LEAVE SHALL BE EXTENDED TO ONLY
THOSE EMPLOYEES WHO ARE AN EMPLOYEE OF RECORD ON OR
BEFORE JULY 01, 2013.
7. THIS TEMPORARY PERSONAL LEAVE SHALL NOT BE INCLUDED IN
ANY PAYOUT PROVISIONS.
I FURTHER MOVE THAT THE DISTRICT MANAGER IS AUTHORIZED TO MAKE
FINAL ADMINISTRATIVE ADJUSTMENTS TO THESE TERMS.
Mr. Wilson SECONDED THE
MOTION.
VOTE:Unanimous.
The motion carried.
DISTRICT MANAGER REPORT
None.
DISTRICT DIRECTOR REPORT
Water Utilities Community Facilities District
Meeting Minutes of July 2, 2013
Page 4 of 9
District Director Frank Blanco stated he did not have a formal
report but had information he wanted to share about a project
that is in conjunction with a public works project.This
involves the area in the northwest corner of the water district.
This area was part of Davis System Water Company at one time so
when the water system went in, some of the services such as the
mains and the connections to the meters were not installed per
the proper specifications.The Maricopa Association of
Governments specifications require a 30 -foot minimum cover to
the service line from the main to the meter.In some cases they
are seeing some depths of about 9 inches to 10 inches that are
substandard.The public works paving project will not have the
pavement go over the existing water main however some of the
grading that needs to be done requires those services to be
lowered.There is a four man water crew working on it and
things are going as smoothly as expected.They are able to
locate the service lines and are able to trench alongside the
lines and drop the service lines to the proper depth.This will
allow the paving project to move forward.It is time consuming
and they are only able to do three or four service connections,
when things go smoothly, per day.It is taking some time to
finish.They are working as much as possible but sometimes they
are up against an issue and there are bad results.There was an
area where the service line itself was not in a straight line
from where it connects to the meter.They were able to locate
it at the main with a locater, however if the line does not go
straight through then it results in a service line that gets
disconnected from the main. Doing this type of work takes the
four men crew away from their normal maintenance which would be
turning valves to make sure they can get a shut down when they
have a main and replacing valves that are faulty or not working
at all.Since they are not able to do their normal maintenance,
they are not able to get a very good shut down.In order to fix
the main they have to turn on a fire hydrant to relieve the
pressure, go in and patch the main and make the connection.
Not only do they have water and mud from the break, they also
have water from the hydrant that was opened because the valves
did not work.This allows them to get a good shutdown.They
are working with public works on a solution to get surface on
the dirt so they can make things move more quickly and not
disrupt our residents.They are talking to their customers
before they go in and do repairs.They are going to do door
Water Utilities Community Facilities District
Meeting Minutes of July 2, 2013
Page 5 of 9
hangers in case the customers are not home so they are made
aware of the repairs.
Utility Director Giao Pham stated he wanted to apologize for not
communicating better with the water district when they got
approval to do the project.They are using their HURF reserve
to pave the necessary streets and did the engineering and
design.They are using the contractor Banicki that Maricopa
County Department of Transportation was already using for the
intersection improvement at Meridian and Southern.They
piggybacked on the intergovernmental agreement with Maricopa
County Department of Transportation which has a pretty
aggressive schedule as far as removing all existing pavement.
Maricopa County Department of Transportation was ready to pave
and public works was on track to get it done by the end of July.
What happened is that a lot of the water services were built to
substandard.Public works was anticipating the services were
below the 30 inches, but apparently they are not.If they were
to try to pave again with their roller without fixing the
services, they would break.He feels they have found a good
solution by allowing the water district with their limited
resources to continue to drop the water services.They are
going to do a chip seal to dissipate some of the dust and to
prevent it from flooding during monsoon.When the water
district is done, they will come back, contact the contractor
and pave it according to the asphalt section.They will make
sure to communicate with everyone involved so they get the right
product.
Chairperson Insalaco stated neighbors had called him
complaining.He was glad to hear they would be putting door
hangers out so residents would know what is going on and realize
the problem is being worked on.
Utility Director Giao Pham stated they may get some questions
asking why Palo Verde was in an out.That was a different
roadway and they were able to use their internal crews because
it is a clear grade.There was not a lot of pounding.It was a
straight grade and easy for them to get in and out.There was
also an alley next Palo Verde.A lot of the services were tied
into the alley.Residents may say it is the same, but it is
different.Even though the streets are next to each other, they
Water Utilities Community Facilities District
Meeting Minutes of July 2, 2013
Page 6 of 9
have different characteristics.They are spending more time
because of drainage issues that have happened in the past.
Mr. Waldron asked if the chip seal has to be taken off before
they can pave it or can they pave over the top of it.
Utility Director Giao Pham stated they can pave over the top of
it.It is expensive putting the chip seal down first, but it
adds years to the structure.
District Manager George Hoffman asked if the time frame is three
to four months for completion.
District Director Frank Blanco stated that is correct.It is
very time consuming and takes a lot of work.They have to be
careful they do not break a line and cause themselves more
flooding.The goal is to get done so they do not cause worse
problems than they already have.
District Manager George Hoffman stated that is going to be a
matter of months to get the services undergrounded.They got
bids on the chip seal.
Utility Director Giao Pham stated he was going to shop around
and try to get the best bid and go from there.
District Manager George Hoffman asked if the chip seal would be
down in two weeks.
Utility Director Giao Pham stated they are working with the
contractor Banicki to see if they can do it cheaper or public
works may utilize their own crew to do it.
Mr. Wilson wanted to know if there would be a public notice sent
out to the residents so they would be aware of what is going on.
Chairperson Insalaco stated he thought they could put all the
information on door hangers for the residents so they would know
when and what was going on.
Utility Director Giao Pham stated they are going to do a two
phase approach of flyers and getting information out to the
Water Utilities Community Facilities District
Meeting Minutes of July 2, 2013
Page 7 of 9
media.They will explain to the residents that in order to get
the asphalt in, they will need to lower the water surfaces.
They will let them know how much time they think it will take
and that they will be putting down chip seal until they actually
pave it in the next three to four months.It will be phase
simple for residents to understand.They will make sure they
are provided contact information so, if they have questions they
can contact public works directly.
District Director Frank Blanco stated the chip seal will go down
even though they will still be working on dropping the water
surface.
DISTRICT TREASURER REPORT
None.
MOTION FOR ADJOURNMENT
) Vice Chairperson Barker
MOVED THAT THE WATER DISTRICT REGULAR MEETING OF JULY 2, 2013 BE
ADJOURNED.
Mr. Waldron SECONDED THE
MOTION.
VOTE:Unanimous.
The motion carried.
ADJOURNMENT
adjourned the meeting at 6:25 p.m.
) Chairperson Insalaco
ACCEPTED THIS 6TH DAY OF AUGUST , 2013,
BY THE CHAIRPERSON AND DISTRICT BOARD OF THE WATER UTILITIES
COMMUNITY FACILITIES DISTRICT,(CITY OF APACHE JUNCTION,
ARIZONA).
SIGNED AND ATTESTED TO THIS 6TH DAY OF AUGUST
2013.
Water Utilities Community Facilities District
Meeting Minutes of July 2, 2013
Page 8 of 9
( 616 t ot-dif
n S. Insalaco
Chairperson
ATTEST:
Kathleen Connelly
District Clerk
Kathleen Connelly F
District Clerk
WATER UTILITIES COMMUNITY FACILITIES DISTRICT MINUTES
CERTIFICATION
I hereby certify that the foregoing minutes are a true and
correct copy of the minutes of the regular meeting of the Water
Utilities Community Facilities District of the City of Apache
Junction, Arizona, held on the 2n0. day of July, 2013.I further
certify that the meeting was duly called and held and that a
quorum was present.
Dated this 8th day of July, 2013.