A. Call to Order
Chairperson Wilson called the meeting to order at 6:02 p.m.
B. Roll Call
Present 7- Chairperson Wilson,Vice Chair Schroeder, Boardmember Cross, Boardmember
Heck, Boardmember Johnson, Boardmember Nesser, and Boardmember Soller
Staff in attendance:
Bryant Powell, District Manager
Matt Busby,Assistant District Manager
Jennifer Pena, District Clerk
Joel Stern, District Legal Counsel
Mike Loggins, District Director
Charles Briggs, Water District Project Manager
Stacy Ramirez, Utility Billing Supervisor
Rita Vineyard, Senior Administrative Assistant
Leslie DeReche, District Treasurer
Connie Chow, District Controller
Evie McKinney, Deputy District Clerk
Al Bravo, Public Information Officer
Robert Wisler, Management Analyst
C. Agenda Items
1. 23-411 Approval of meeting minutes of June 20, 2023.
Boardmember Soller made a motion to approve the meeting minutes of the June 20,2023,
meeting.Boardmember Nesser seconded the motion.
2. 23-412 Presentation, discussion, and consideration for approval of a construction
agreement with Garney Companies, Inc. for the installation of 5,205 linear feet
of a 16" Bi-directional transmission main to be installed from the Apache
Junction Water District in the amount of$1,155,007.17.
Boardmember Heck made a motion that the construction Agreement between Water Utilities
Community Facilities District and Garney Companies,Inc.for the installation of 5,205 linear feet of
a 16"bi-directional transmission main using the cooperative use portion of the City of El Mirage
Job Order Contract Water and Wastewater Projects—PW19-J00O2 for a total not to exceed
$1,155,001.17,be approved.Boardmember Nesser seconded the motion.
District Director Mike Loggins presented an overview of a construction Agreement with Garvey
City of Apache Junction,Arizona Pagel
Water Utilities Community Facilities Meeting Minutes August 15,2023
District
Companies, Inc.for the installation of 5,205 linear feet of 16" bi-directional transmission main to
be installed from the Superstition Area Water Plant to the Apache Junction Sewer District
(AJSD).The pipe was purchased in Fiscal Year 2023 and the installation of the pipe was
budgeted for Fiscal Year 2024. Initially, the main will be used to pump Central Arizona Project
(CAP)water to the AJSD for recharge and in the event the CAP water is not available, then
changing the direction of the flow and using effluent water from the AJSD as direct potable
reuse, using advance filter or advanced purification facility. This is a project that has been
ongoing for the last couple of years and once complete, it will tie the two Districts together. The
project is approximately$1.1 million, and due to the increase costs of labor and material the
amount is slightly over the original budgeted amount of$800,000.
D. District Manager Report
No report.
E. District Director Report
3. 23-413 Presentation, discussion, and update on Water Infrastructure Finance
Authority of Arizona Water Conservation Grant.
Mr. Loggins presented an overview of the Water Infrastructure Finance Authority(WIFA)Water
Conservation Grant that the District applied for in May, 2023.The grant, in the amount of
$1,065,845.00,will be used for an Advanced Meter Infrastructure Project that will allow for the
installation of radios on every meter in the District, and towers that will transmit hourly meter
reads as opposed to every 30 days.This will assist with water conservation by notifying the
District sooner when there is a leak.Another benefit includes tracking water loss throughout the
system. In July, Mr. Loggins had a meeting with WIFA's grant committee.At that meeting, the
committee recommended the District for approval and moved the grant to the WIFA board for
consideration. Mr. Loggins said he would be attending the board meeting on August 16, 2023, to
find out if the District was approved for the grant. If approved,the project will take approximately
one year to complete.
4. 23-414 Presentation, discussion, and update on Utility Billing software.
Mr. Loggins presented an update on the new Utility Billing Software implemented the beginning
of August. The District sent post cards and flyers to customers to keep them informed of the
changes. Customer feedback has been positive, and office staff is working with the customers
who need assistance.
5. 23-415 Presentation, discussion, and update on District wide water system.
Mr. Loggins presented an update on the water system.The Superstition Area Water Plant has
been pumping at capacity since April.The increase in demand is due to the construction in the
state land area. Production at Well 5 has dropped and the pump is being pulled to see why this
is occurring. Well 6 is being used to support with peak demands while Well 5 is down.
Construction continues on the water campus 3 with a completion date of January or February of
2024.The District has taken over the transmission and distribution lines from the developer.
City of Apache Junction,Arizona Page 2
Water Utilities Community Facilities Meeting Minutes August 15,2023
District
District Manager Bryant Powell introduced the presentation of the One Water Our Water video.
The video explains who the water service providers are in Apache Junction, where the water
they provide comes from and how it is distributed to our citizens.
F. District Treasurer Report
No report.
G. Adjournment
Chairperson Wilson adjourned the meeting att--6:25 p.m.
ACCEPTED THIS��DAY OF ��Q1}f�0_M�/1 2023, BY THE CHAIR
PERSON AND DISTRICT BOARD OF THE WATER UTILITIES COMMUNITY FACILITIES
DISTRICT, (CITY OF APACHE JUNCTION,ARIZONA).
SIGNED AND ATTESTED TO THIS DAY OF QdZ.AM ' 2023.
f r
WALTER"CHIP"WILSON
Chairperson
ATTEST:
4vte—
JENN(FE PENA
District Clerk
WATER UTILITIES COMMUNITY FACILITIES DISTRICT MINUTES CERTIFICATION
I hereby certify that the foregoing minutes are a true and correct copy of the minutes of the
regular meeting of the Water Utilities Community Facilities District of the City of Apache
Junction,Arizona, held on the/9 day of � 1? adnA14 , ,2a3
I further certify that the meeting was duly called and held and that a quorum was present.
Dated this I q day of �4LM&4 2023.
LA�A� V,2to'—
JEN I ER PENA
District Clerk
City of Apache Junction,Arizona Page 3